Microsoft's exit from an Nscale lease is a reality check for neoclouds (opens the source in a new tab)

KKReckons explainer: Nscale's $35bn IPO target and why Lex says neoclouds face a reality check.
Original graphic: KKReckonsView full size ↗
  • Microsoft pulled out of leasing capacity at Nscale's planned data centre in Essex, which may not get power until after 2030, as Nscale targets a New York listing at a $35bn valuation.
  • An FT Lex column says Neocloud A newer cloud company, such as CoreWeave or Nscale, that rents out AI chips, often funded with debt. need power, chips and upfront financing at once, so their big order books carry heavy execution risk; Anthropic and Microsoft fill most of Nscale's backlog.
  • Valued on peers' multiples, Lex argues, Nscale is worth far less, while bigger players with ready capacity stand to win.
$35bn
target IPO valuation
~$6bn
Lex's peer-based value

Why it matters If power, not demand, decides who delivers AI capacity, the neocloud boom may consolidate into firms that already have grid connections.

Other side The Essex site was a small slice of Microsoft's spending with Nscale, and its other contracts may hold; one cancelled lease need not sink the model.

Read the full 21 Oct edition →Catch up on past editions

More on:Anthropic 32Microsoft 17

Today’s edition is ready

Read deep. Think clearly. Stay curious.

A daily visual briefing on the stories that matter: India, the world, and what’s next.

Read Today’s Edition →Get it by email ↗

Free · 50 editions and 359 stories so far · Unsubscribe anytime

Emails are sent by beehiiv; your address is used only for this newsletter. Privacy · Editorial standards